  1. Cable and terminate Boiler Control Unit Honeywell Environmental Control Unit and associated Thermostats and motorised valves. All remote peripherals forming part of the “Megaflow System”. Pressurised tank maintains constant water flow and pressure to all Showers, Baths and Domestic appliances; Dishwasher and Washing machine including additional sink unit in utility room.

  2. Renovate and install 2 off Coughtree Surface Bulkhead light fitting.

  3. Commission builder to install stud wall with opening to section garage.

  4. Cut, dress and lay Ceramic Floor Tiles, to garage floor area.

  5. Install wood Floor covering to study

  6. Construct built-in desk

  7. Construct built-in shelving

  8. Install Router to distribute LAN and connect to BT Wireless Router LAN Output.

  9. Install 3 off LAN Data Outlet

  10. Install co-axial outlet to Satellite Dish

  11. Install 8 off dedicated 2 Gang 13A Switched Socket outlet

  12. Install Data and Power Trunking to walls.

  13. Install modular pelmet lighting beneath shelving.

  14. Install Main Earth Bonding to Gas supply and cross bond.

  15. Install removable shelving and small designed and constructed open shelf book case.

  16. Install Fan with integral Centre Lamp to ceiling controlled by 1 Gang 1 Way Switch including 3 LED Spot light chrome fitting controlled by Pull-switch.